Selection
How to compare two blow molding quotations line by line
Two offers for the same bottle can describe machines that differ by a third of their output, and neither headline figure explains why. Compare them on the six variables that create the difference, then read the four clauses that decide what you actually receive.
Why the headline figure is not comparable
A quotation is a machine description with a number attached. That number is the sum of screw diameter, die head count, cavities, station type, automation and the parts list, in roughly that order of influence. Change one and you have changed the machine, not the seller’s margin.
So compare the specification first and the total second. If two offers still differ by more than 15% once the six variables are matched, the gap is scope. If they differ by less, the machines are close and the decision is about service.
Keep one sheet, one column per supplier, and force every claim into a cell.
Normalise six variables before you read any total
- Screw diameter and L/D ratio. A 75 mm screw and an 85 mm screw are different machines for the same bottle: more plastic per hour, longer residence time, different melt quality.
- Die head count. Output scales with heads, not with clamping force. Two heads at 9 s give twice the bottles of one head at 9 s.
- Cavities, and who owns the mold. A four-cavity mold offered against a two-head machine is arithmetic that does not close.
- Station type. Single or double changes output and machine length. A double station needs two molds, or one two-station mold.
- Automation. De-flashing, leak testing, conveying and weighing. Each item is either inside the scope or in a second offer.
- Parts list. What ships with the machine and what is consumable. Ask for items and quantities, not for an assurance.
A comparison sheet you can fill in
Ten rows, filled from the quotation rather than from the conversation.
| Line to record | What to write down | Why it decides the comparison |
|---|---|---|
| Screw diameter and L/D | Millimetres, ratio, screw material | Sets plastic capacity and melt quality |
| Die head count | Number, and center distance between heads | Sets output per cycle |
| Cavities and mold ownership | Number, and who supplies the mold | Sets output and tooling scope |
| Station type | Single or double | Doubles output, or changes nothing |
| Clamp force | kN, and maximum mold height | Sets the largest container the machine can hold |
| Cycle time quoted | Seconds, at a stated bottle weight | Converts directly into bottles per hour |
| Installed power | kW, and voltage and phase | Decides whether your supply is adequate |
| Automation included | Item by item, supplier named | Usually the invisible third of a line |
| Parts list | Items and quantities | Decides first-year downtime |
| Commissioning | Days included, and who attends | Decides how production starts |
Four clauses that decide the real difference
- Scope. List every included item and close the list with everything else excluded. A vague scope always favours the seller.
- Spare parts. Heaters, seals, blow pins, solenoid valves and proximity switches: two of each, named.
- Commissioning. Who sends the engineer, for how many days, and who provides mold, material, power and water for the trial.
- Warranty boundary. What is covered, what voids it, and how a claim is handled across a border.
Read the warranty clause and the utilities clause together. Most rejected claims trace back to water temperature or voltage that the buyer was never told to control.
Bare machine against complete line
The commonest comparison error is a bare machine against a complete line. A line carries chiller, compressor, dryer, conveyor, leak tester, granulator and the panel to run them. Most of that list is invisible in a headline figure.
Normalise by asking both suppliers for the same package: one machine, one mold, the ancillaries to run it, commissioning and a trial at your container weight.
Where to go next
- Blow molding line configuration — what a complete line contains, item by item.
- Auxiliary equipment — the ancillaries that decide whether two offers are comparable.
- Single versus double station — the variable that doubles output without changing the bottle.
- Blow molds — the part of the quotation that is easiest to leave out.
- Services and commissioning — what attends the machine after it arrives.
Need a machine sized for your container?